By Francis Allan L. Angelo

LOOMING power and water crises are bugging the Iloilo City government this holiday season.

For one, the National Power Corp. (Napocor) has yet to install the 15 units of modular diesel power generator in Iloilo City to augment the metropolis’ electricity. With this, Mayor Jerry Treñas said he is apprehensive power blackouts will occur when the city celebrates Christmas and New Year.

Last year, the whole metropolis was plunged in darkness but Panay Electric Co. (Peco) and Panay Power Corp. said the outages were man-made and technical in nature.

The generator sets supposed to be installed before December in a Peco-owned lot at Brgy. Bolilao, Mandurriao are part of Napocor’s commitment to the city to supply 15 megawatts of power through a direct interconnection agreement with Peco mandated by the Energy Regulatory Commission.

Early this year, Napocor installed the first batch of the same 15 generator sets at the Capiz Electric Cooperative compound in Panit-an, Capiz to augment power supply in the province and parts of northern Iloilo.

This is in response to the order of President Gloria Macapagal-Arroyo for the Department of Energy and Napocor to solve the acute power shortage in Panay, especially in Iloilo City.

Meanwhile, Panay Power Corp. continues as the main supplier of electricity to Iloilo City which has currently a peak demand of 76MW. This December, the city’s power demand may exceed 90MW.

Aside from power shortage, the City government is also grappling with acute water shortage. The problem is more pronounced in the 11 Waterfront barangays who were supposed to meet the Metro Iloilo Water District (MIWD) board of directors around 2pm Thursday. The meeting did not push through as the punong barangays walked out after an hour of waiting for the directors to meet them.

The meeting was aimed at resolving the water shortage at the Waterfront whose residents are now restive over MIWD’s minimum fee of P159. Residents said no water comes out of their faucets but they continue to pay the water firm.

Punong Barangay Roberto Divinagracia said Waterfront barangays are forced to buy water by the gallons from private sources.

Divinagracia, president of the Association of Barangay Captains-Iloilo City proper district, said they will make a position letter asking MIWD to waive the minimum fee until normal water supply returns to the waterfront area.

BILLING POLICY

In a news release issued yesterday, the MIWD issued a new billing policy on areas that have no water supply.

In consonance with the resolution passed by the MIWD board of directors the other day. the water firm decided to condone the payment of water bills in some MIWD service areas experiencing water shortage.

Engr. Edgar Calasara, MIWD officer-in-charge, said water bills which have zero to five cubic meter (0-5cu. m.) consumption reading shall not be delivered anymore provided that the water district’s engineering department certifies that such area has no water for the period.

Water bills that were delivered to concessionaires shall not be paid provided that said billing bears 0-5 cu. m. consumption reading and are certified by the Engineering Department as within an area without water supply for the period.

If the consumer has paid the bill in any authorized MIWD collecting banks or payment outlets, the amount shall be retained and considered advanced payment for future water bills.

Calasara said the policies shall be effective November 1 to December 31, 2008, unless extended by another board resolution.

He, however, said that consumers in areas where there is a steady supply of water are obliged to pay their monthly water bills.

Calasara also assured the consumers that MIWD is doing everything to fast track the permanent repair of its damaged pipe and the ongoing cleaning of its reservoir in order to restore water in areas where there is intermittent supply, particularly in Jaro and the Waterfront.

 