By Francis Allan L. Angelo

THE Metro Iloilo Water District (MIWD) has moved the awarding of contracts to three bulk water suppliers next year after the post qualification process of the bids and awards committee.

In an interview with Serbisyo Publiko hosted by Iloilo City Councilor Perla Zulueta over Sky Cable Sunday, Engr. Adrian Moncada, MIWD director, the bulk water supply contracts will be awarded January 2010.

Moncada said they expect the contractors to start working on their facilities by February 2010.

“Six months after we awarded the contract, we can expect 20,000 cubic meters of additional water from the suppliers,” Moncada said.

Maynilad Water Services Inc., Solerex Water Technologies, Inc. and Abejo Builders Corp. offered the lowest bid for four injection points where the bulk water supply will be transmitted.

Maynilad won the contract for the Pavia injection point, which has a capacity of 10,000 cu m, at P11.98 per cu m.

Solerex got the Leganes injection point (2,000 cu m) at P14.28 per cu m.

Abejo will supply 8,000 cu m of water through the San Miguel and Ungka (Jaro) injection points at P13.98 per cu m.

Dr. Danilo Encarnacion, MIWD director, said the suppliers can draw water from surface or underwater sources depending on the location of the injection points.

Encarnacion said the winning bidders will have to construct their own facilities such as water treatment facility.

The MIWD also clarified the issue raised by a municipal councilor of Pavia who claimed that they were bypassed in the bidding process.

Moncada said the bidding was internal to the MIWD and there is no need to seek clearance from the host towns.

“Once the winning bidders start constructing their facilities, they will have to seek regular permits and other clearances from the municipal government concerned,” Moncada said.

Moncada reiterated that they will not jack up water rates after the bulk water supply is implemented.

Advertisements